Garage Work Remains on Schedule; Installation of Big Pieces Continuing in Coming Weeks
Good news on the State Street Garage expansion: The project remains on schedule for completion in early June, and a few hundred additional parking spaces are expected to become available in mid-March as the construction moves to its next phase.
Over the coming two weeks, the 300-foot-tall yellow LR Liebherr 1300 crane deployed on State Street will continue hoisting big slabs of precast concrete to be installed on the west side of the garage. And then the big-piece installation will be done.
The $11 million project is adding two more decks and 570 new parking spaces at State Street Garage.
The new decks won’t open for three more months, as the construction work is finalized. The additional parking spaces that are becoming available in mid-March are existing parking spaces which now are out of commission due to the staging for the installation. Barriers will be coming down, and spaces on what had previously been the top levels of the garage will return back into use.
Meanwhile, State Street – the road itself – is expected to reopen by April 1. Once the crane is gone in mid- to late March, crews will remove the dirt and gravel used as padding.
Work will continue on the State Street exit out of the garage, and once that concludes and State Street reopens, there will once again be two exits out of the garage (onto State and onto Union Avenue) and three entrances into the garage (from State, Union and Clinch Avenue). All the extrances, exits and elevators will be open and operational as the project nears its June completion.
Posted by
evreeland
On 05 March, 2019 at 5:10 PM
Recent Posts
First-day Photo Gallery of Top Floors of State Street Garage
Now open! New Decks in State Street Garage Can Accommodate 570 Vehicles
State Street Garage Work Nearing Completion
June 12: State Street Garage Expansion to be 'Substantially Completed'
State Street Garage Expansion in Final Stage of Construction
Garage Work Remains on Schedule; Installation of Big Pieces Continuing in Coming Weeks
Downtown Parking Tip Sheet: Feb. 1
Precast Concrete Installation Moves to Garage's West Side; $11 M Expansion on Schedule
Downtown Parking Tip Sheet: Jan. 18
Downtown Parking Tip Sheet: Jan. 4
Post Categories
City Services
Downtown
Content Alert Subscription
Blog Feeds
Podcast Feeds
Subscribe to Email Alerts