Northwest Greenway Connector Nears Completion
Sometime last week, the $1.7 million Northwest Greenway Connector began to actually
look
like a nearly finished greenway.
That's because contractor crews have moved on past the preliminary tasks such as utility relocations, building retaining walls and installing erosion control devices to the good part - laying down asphalt, landscaping and finessing the final touches.
View from Ball Camp Pike, where the greenway traverses between residences and Badgett Fields
The paving began with the warm weather in March, and by last week, Adams Contracting crews had completed about 85 percent of the asphalt work. The remaining paving is expected to be finished this week, barring heavy rain.
So this key half-mile stretch of trail between Victor Ashe Park and the state-funded pedestrian bridge spanning Western Avenue at Ball Camp Pike, while not open yet, is easy to envision. It's getting close.
What's left to be done, besides the final paving?
City Engineering Manager Amanda O. Koenig says crews will be moving dirt and sodding and seeding around the greenway. Handrails, signs and about 150 feet of guardrail still need to be installed.
Above and below: Different views of a retaining wall on Ball Camp Pike
The Northwest Greenway Connector is strategically important: It will link the 8.9 miles of greenways and sidewalks around the park with another 7.2 miles of sidewalks on Western Avenue and Schaad Road.
Within a three-mile radius of Victor Ashe Park, a walker can access a total of 73 miles of greenways and sidewalks.
The connector is anchored on its southern end by a $3 million 500-foot-long pedestrian bridge over Western Avenue that was funded and built by the Tennessee Department of Transportation.
The bridge is intentional and significant, because the City's long-range plan is to eventually extend the greenway southward to connect Western Avenue at the bridge to Middlebrook Pike and on to the Third Creek Greenway. This next phase of work to extend the greenway to Middlebrook Pike is fully funded, and construction will begin in 2023 once design work is finalized and easements have been acquired.
Here's a view of the section of greenway looking toward Victor Ashe Park.
Posted by
evreeland
On 22 March, 2022 at 2:50 PM
Recent Posts
Wide, Tree-lined Sidewalks Will Connect to Stadium - and So Will Future Greenways
Stadium Update: Concrete Poured for Plazas, First Trees Planted, Streetscapes Improvements Under Way
Crime in Knoxville is Down - and 2/3 of Residents in East Knoxville TLC Zone See Positive Change
Work Begins on Sevier Avenue Streetscapes; Look for Regularly Scheduled Project Updates
Postcard Photo of Augusta Quarry in Snow: Check Out the 9 New Swim Platforms!
Revolutionary War Veteran Honored With Victor Ashe Park Gravesite Restoration
Smokies Baseball and One Knox Soccer: Careful Collaboration Makes for 'A Great Fit'
12 Days of Public Service
Popular Market Square Ice Rink Set Attendance Record in 2023; On Pace to Set New Record This Year
Bike/ped safety improvements on Henley Bridge benefit all road users
Archives
February 2025 (2)
January 2025 (5)
December 2024 (5)
November 2024 (1)
October 2024 (5)
September 2024 (1)
August 2024 (2)
July 2024 (2)
June 2024 (1)
May 2024 (1)
April 2024 (4)
Group Blogs
City Blog
KAT Blog
KPD News & Alerts
Magnolia Avenue Streetscapes Project
More...
Post Categories
City Events
City Services
Cumberland Ave.
Downtown
Government
KAT
Mayor Kincannon
Meetings
Neighborhoods
Outdoor & Recreation
Public Safety
Redevelopment
Road Work
South Waterfront
Sustainability
Content Alert Subscription
Blog Feeds
Podcast Feeds
Subscribe to Email Alerts