Safety Complex Updates
Week 20: Work Expands to 5 S...
Week 20: Work Expands to 5 St. Mary's Hospital Buildings; Central Wing Coming Down
Mass demolition of the Central Wing (right) at the Annunciation Wing (left) is underway.
Eventually, the entire North Campus and Central Wing will be cleared, leaving a large tract of vacant land and the iconic 1929 original hospital building available for private redevelopment.
This month, the work to transform the vacant St. Mary's Hospital North Knoxville campus into a new City Public Safety Complex is expanding, with contractor crews tackling tasks right now in the Central Wing, the Central Wing Annex, the Women's Pavilion, the Marian Wing and the Annunciation Wing.
Pictured above is the Annunciation Wing, where NEO Corp. crews are wrapping up lower-level abatement, and the Central Wing, where Renascent is continuing with a mass demolition.
Environmental Abatement Inc. crews are continuing with selective demolition in the Women's Pavilion and in the above-ceiling areas in the Central Wing Annex. Last week, they worked their way down the demolition punchlist for the LL3 floor in the Central Wing Annex and did above-ceiling work on the fifth and sixth floors.
NEO Corp. this week is wrapping up abatement in the Annunciation Wing's LL1 and LL2 floors.
Del-Air last week completed the final walk-throughs of the original 1929 building to verify that all piping has been cut and capped.
The City is investing $40 million to overhaul the vacated hospital and transform it into a combined Public Safety Complex that will house Police, Fire, City Court and Pension Systems operations. Another $6.5 million is being spent to clear parts of the northern end of the campus to accommodate future private redevelopment. The iconic and stately marble-accented 1929 building is being carefully preserved to serve as an anchor when the campus' north end is privately redeveloped.
Currently, Lincoln Memorial University is remodeling the former Magdalene Clark Tower into classrooms.
Renascent crews last week were doing soft interior demolition in the Marian Wing.
Posted by
evreeland
On 10 July, 2020 at 12:28 PM
Recent Posts
Public Safety Complex Move-in to Begin in January
Welcome, Neighbor! LMU Opens College of Dental Medicine, Clinic Next to City Public Safety Complex
Crews to Repair Original Brick Façade at Public Safety Complex
Week 125: Heading into Long Final Home Stretch
Week 110: Work Progressing in All 3 Buildings, Plus Walls Going Up at New Court Building
Week 109: Check Out the Progress with City Court Construction
Week 100: Public Safety Complex is Two-Thirds Completed!
Week 97: Drywall going up!
Week 93: More Interior Walls Going Up
City, County Moving Ahead With Behavioral Health & Urgent Care Facility Next to Safety Complex
Group Blogs
City Blog
KAT Blog
KPD News & Alerts
Magnolia Avenue Streetscapes Project
More...
Post Categories
Safety Complex
Content Alert Subscription
Blog Feeds
Podcast Feeds
Subscribe to Email Alerts