Week 54: Pouring Concrete - ...
Week 54: Pouring Concrete - Lots of It
The last weekday in February was nicknamed "Pour Day," because that was the day when Al Blankenship Enterprises employees poured 100 cubic yards of concrete.
A hundred yards - that's the length of the nearby Fulton High School football field. Imagine the equivalent of 100 small boxes placed side-by-side the length of a playing field, each box 3 feet wide and 3 feet tall - that's how much concrete was poured on Feb. 26 at the Public Safety Complex. It was enough material to fill 11 concrete trucks.
For weeks, Blankenship crews have been forming a new foundation wall near where a new City Court courtroom will be built, abutting the north side of the former Central Wing Annex, as it was called when it was part of St. Mary's Hospital in North Knoxville.
This week, Blankenship is forming and pouring more concrete wall, as the City's Public Safety Complex is definitely taking shape.
When it opens in summer 2022, the Public Safety Complex will house Police, Fire, Pension System and backup E-911 operations in the vacated hospital's repurposed Professional Office Building, Central Wing Annex and Women's Pavilion. A new single-story City Court is being constructed, adjoining the complex.
Meanwhile, Lincoln Memorial University is offering nursing classes in the Magdalen Clarke Tower, with plans for a formal west-end entrance and a lush quadrangle-style public green space.
The stately 1929 Building - free-standing and unobscured for the first time in decades - will anchor future private redevelopment on the northern end of the campus.
The iconic old building is being carefully preserved. Contractor crews are tending to everything from masonry work on the parapet in January to, last week, Renascent crews completing repairs to the alcove roof and Messer Construction completing the installation of exterior temporary partitions.
Posted by
evreeland
On 04 March, 2021 at 12:41 PM
Recent Posts
Public Safety Complex Move-in to Begin in January
Welcome, Neighbor! LMU Opens College of Dental Medicine, Clinic Next to City Public Safety Complex
Crews to Repair Original Brick Façade at Public Safety Complex
Week 125: Heading into Long Final Home Stretch
Week 110: Work Progressing in All 3 Buildings, Plus Walls Going Up at New Court Building
Week 109: Check Out the Progress with City Court Construction
Week 100: Public Safety Complex is Two-Thirds Completed!
Week 97: Drywall going up!
Week 93: More Interior Walls Going Up
City, County Moving Ahead With Behavioral Health & Urgent Care Facility Next to Safety Complex
Group Blogs
City Blog
KAT Blog
KPD News & Alerts
Magnolia Avenue Streetscapes Project
More...
Post Categories
Safety Complex
Content Alert Subscription
Blog Feeds
Podcast Feeds
Subscribe to Email Alerts