Safety Complex Updates
Week 109: Check Out the Prog...
Week 109: Check Out the Progress with City Court Construction
In late January, the new City Court building went vertical - steel columns in place, no longer just an empty plot of ground and a drawing board plan.
Check out the progress with the City Court construction this month at the City's Public Safety Complex in North Knoxville, next to Fulton High School:
The transformation of the vacated St. Mary's Hospital into a new Public Safety Complex - now in its 109th week - is scheduled to be finished by the end of this year.
The site will be a mix of government offices, college classrooms, private redevelopment and public green space in what had been, two years ago, a cramped cluster of vacant, obsolete buildings.
The City razed the old buildings that could not be repurposed and is reconstructing three empty buildings - the former Professional Office Building, Central Wing Annex and Women's Pavilion - to serve as a combined complex for the Police and Fire Departments, Pension System, and City Court and E-911 backup operations. It's a $55.8 million public investment.
Next door, Lincoln Memorial University is building out the former Magdalen Clarke Tower, a $40 million private investment that will create educational opportunities for hundreds of nursing and dental students each year.
New housing is envisioned on the north end of the former hospital campus, which the City cleared to accommodate future private redevelopment. The historic 1929 Building was carefully preserved and protected.
In the near future, the City and County also will be jointly converting the 25,000-square-foot former St. Mary's Ambulatory Surgery Center on the south end of the site into an urgent care and behavioral health facility.
Posted by
evreeland
On 29 March, 2022 at 1:45 PM
Recent Posts
Public Safety Complex Move-in to Begin in January
Welcome, Neighbor! LMU Opens College of Dental Medicine, Clinic Next to City Public Safety Complex
Crews to Repair Original Brick Façade at Public Safety Complex
Week 125: Heading into Long Final Home Stretch
Week 110: Work Progressing in All 3 Buildings, Plus Walls Going Up at New Court Building
Week 109: Check Out the Progress with City Court Construction
Week 100: Public Safety Complex is Two-Thirds Completed!
Week 97: Drywall going up!
Week 93: More Interior Walls Going Up
City, County Moving Ahead With Behavioral Health & Urgent Care Facility Next to Safety Complex
Group Blogs
City Blog
KAT Blog
KPD News & Alerts
Magnolia Avenue Streetscapes Project
More...
Post Categories
Safety Complex
Content Alert Subscription
Blog Feeds
Podcast Feeds
Subscribe to Email Alerts