December 17, 2019

The $6.35 million North Central Street Project is nearing completion with the landscape installation almost complete.

Mayor Rogero, City Council members, City staff, TDOT staff, representatives of the project team and neighborhood stakeholders will cut a ribbon to celebrate on Wednesday, Dec. 18, 2019 at 11 a.m. near the intersection of Baxter Avenue at Central Street.

The project covers 13 blocks and includes 43,000 square feet of new green space in addition to major infrastructure improvements with water mains, fire hydrants, and increased multi-modal function, making it friendly to pedestrians, bicyclists, transit users, as well as drivers.

The City’s project includes replacing deteriorating storm water lines, repairing and replacing damaged sidewalks, installing new bulb-outs to define on-street parking and provide areas for landscaping, better-marked bike lanes, resurfacing the street, and creating a linear park near Baxter Avenue.

The upgraded area runs from Depot Avenue on the south end of the project through the intersection at Broadway and north to Woodland Avenue, approximately 1.1 miles.

Prior to the City’s construction, Knoxville Utilities Board (KUB) replaced more than 8,000 linear feet of water main and 26 fire hydrants.





November 4, 2019


Crews have placed asphalt along N. Central from 3rd to 4th





July 08, 2019

TRAFFIC CONTROL AND SAFETY
No traffic issues to report

PROGRESS SINCE May 2, 2019
Milling and overlay is complete
All concrete curbs, bump outs, gutter pans, and sidewalks are complete
Sandblasting of specialty concrete is complete
Final striping is ongoing and should be complete 
Planting soil installation and mulch placement is ongoing
Signage installation is ongoing
Installation of remaining benches and bike racks is on going
All known damaged concrete has been replaced
Concrete infill at Oklahoma is complete

TWO-WEEK LOOK AHEAD
Complete remaining work, clean up and demobilize





May 20, 2019

TRAFFIC CONTROL AND SAFETY

Expect occasional lane closures for milling and paving operations. Traffic will be maintained by flagging or detours.

PROGRESS SINCE May 2, 2019
Milling and overlay from Depot to Baxter is complete
Driveway at 1221 N Central has been removed and replaced with sidewalk
All concrete on south side of Baxter is completed 
Curbs on north side of Baxter 50% complete
Median island curbs from Pearl to end of project are complete
Island at 1306 North Central was pulled back to allow driveway access
Dig outs are complete from Baxter to Oklahoma

TWO-WEEK LOOK AHEAD
Mill and overlay Central from Baxter to end of project
Continue work on the north side of Baxter
Dig outs from Oklahoma to end of project





May 02, 2019

TRAFFIC CONTROL AND SAFETY

Expect occasional lane closures for milling and paving operations. Traffic will be maintained by flagging or detours.

PROGRESS SINCE April 4, 2019
Driveway and loading dock entrance at Three Rivers Market are complete
Curbs, sidewalks, bench pads, and gutter pans on south side of Baxter are 90% complete
Median islands from Bearden to Pearl are complete
Milling from Depot to Bernard is complete
Dig outs done from Depot to Bernard
Excavation on the north side of Baxter is ongoing

TWO-WEEK LOOK AHEAD
Complete work on the south side of Baxter
Begin work on the north side of Baxter
Complete milling from Bernard to Baxter
Dig outs from Bernard to Baxter
Pave from Depot to Baxter





April 04, 2019

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE March 7, 2019
Interconnect cable installation is ongoing
Southwest corner of Baxter Avenue has been poured
Curbs and sidewalks on the east side of N Central have been poured from Anderson to Baxter
Bus pad on Central at Three Rivers Market has been poured
Large bump out at the northeast corner of Baxter has been poured
Asphalt patching along Central is complete
Benches on North Central have been installed except for benches at the Knox County Central building
Excavation on the south side of Baxter is ongoing

TWO-WEEK LOOK AHEAD
Begin work on the north side of Baxter Avenue





March 07, 2019

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Feb. 22, 2019
Bike racks on Central have been installed
Above-grade planters have been installed
Interconnect cable installation is ongoing
Curbs and sidewalks on the west side of N Central have been poured from Anderson to Baxter
Driveway at 1121 N Central has been poured
Southwest corner of Baxter has been poured
Planting beds have been cleared of trash, existing weeds have been sprayed, and pre-emergent has been applied

TWO-WEEK LOOK AHEAD
Begin work on the south side of Baxter Avenue





February 21, 2019

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Feb. 7, 2019
Old signal pole and sign pole on the north side of West Anderson have been removed
Pedestrian signal at Bernard is now active
Curbs, sidewalks, and ramps on both sides of West Anderson have been poured
Asphalt removal and grading for bump-outs between Anderson and Baxter has begun

TWO-WEEK LOOK AHEAD
Complete curbs, bump outs, and driveways on the west side of N Central Street working toward Baxter Avenue





February 07, 2019

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Jan. 25, 2019
Curbs, sidewalks, ramps, and bus shelter pad on the west side of N Central Street working toward Baxter have been poured
New signals at Anderson have been activated
Planting soil on the east side of Central has been placed to Scott Avenue.

TWO-WEEK LOOK AHEAD
Continue curbs, bump outs, and driveways on the west side of N Central Street working toward Baxter Avenue





January 25, 2019

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Jan. 10, 2019
Curbs, sidewalks, ramps, and bus shelter pad on the west side of N Central Street working toward Baxter are up to date
De-mobilizing from laydown yard

TWO-WEEK LOOK AHEAD
Continue curbs, bump outs, and driveways on the west side of N Central Street working toward Baxter Avenue
Resume work on signal system at Anderson 





January 10, 2019

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Dec. 13, 2018
Curbs, bump outs, and driveways on east side of Central between Anderson and Scott have been poured
Asphalt  has been patched on the east side of Central between Anderson and Scott
Signal cabinet has been relocated and the new signals have been activated at Bernard
Signal pull box at Baxter has been relocated

TWO-WEEK LOOK AHEAD
Curbs, bump outs, and driveways on the west side of Central starting at Scott and working back toward Baxter
KAT shelter at 1401 Central will be removed by 1/14/19
Resume work on signal system at Anderson once KUB overhead work is complete





December 13, 2018

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Nov. 29, 2018
Curbs, bump outs, and driveways between Baxter and Anderson on the east side of Central have been poured
Bump out and sidewalks on both sides of East Anderson have been poured
The large bump-out/sidewalks at the southeast corner of Baxter have been poured
New signal activated at Broadway

TWO-WEEK LOOK AHEAD
Continue to work toward activating new signals at Bernard, cabinet pedestal is being relocated
Work on curbs and sidewalks on North Central until design issues on Baxter are resolved and overhead utility relocations are completed
SCI will work four-day weeks after Christmas and New Year's, weather dependent





November 29, 2018

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Nov. 13, 2018
Bench pad closest to Baxter Avenue on the east side of North Central has been removed and the sidewalks have been re-poured
Radius curbs at southeast corner of Baxter Avenue have been poured to 20' radius
The large bump-out/sidewalks at the southeast corner of Baxter have been poured
New signal mast arms installed at Broadway
New signals activated at 5th intersection
Bump-out curbs at East Anderson have been poured

TWO-WEEK LOOK AHEAD
Continue to work toward activating new signals at Broadway, Bernard and Anderson
Work on curbs and sidewalks on North Central 





November 13, 2018

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Nov. 1, 2018

Bench pad closest to Baxter Avenue and sidewalks south of Baxter have been removed
Radius curbs at southeast corner of Baxter Avenue have been formed to 20' radius
New signal mast arms installed at 5th and Bernard
All new pedestrian signal poles are installed
New traffic signal at Baxter Ave. is complete

TWO-WEEK LOOK AHEAD
Continue to work toward activating new signals at 5th, Broadway, Bernard and Anderson
Place planting soil on south side of Baxter Ave.
Work on curbs, sidewalks, and bench landings on south side of Baxter Ave.





November 01, 2018

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Oct. 18, 2018
KUB has completed work to relocate the gas line in Baxter Ave.
Planting soil has been placed to Baxter Ave.
Storm drainage work on Baxter Ave. is complete
All storm drainage work is complete
New traffic signal at Baxter Ave. is complete

TWO-WEEK LOOK AHEAD

Continue to work toward activating new traffic signals at 5th, Bernard and Anderson
Place planting soil on south side of Baxter Ave.
Begin work on curbs, sidewalks, and bench landings on south side of Baxter Ave.





October 18, 2018

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Oct. 4, 2018
KUB is continuing to relocate the gas line at Baxter Ave.
Curbs and sidewalks have been poured to halfway between Pearl Place and Baxter Ave.
Planting soil has been placed from Bearden Place to Pearl Place and is currently being placed for Knox County Building to Baxter Ave.
Storm drainage work on Baxter Ave. has resumed
Progression is flying arms at Baxter and Anderson avenues
Change order storm at Three Rivers Market has been installed

TWO-WEEK LOOK AHEAD
Signal system infrastructure work continues across the project
Complete curbs, sidewalks and bench landings from Knox County Building to Baxter Ave.
Complete storm work in Baxter Ave.





October 04, 2018

TRAFFIC CONTROL AND SAFETY

No closures at this time.
 
PROGRESS SINCE Sept. 24, 2018
KUB has begun relocating the gas line at Baxter Ave.
Curbs and sidewalks across Knox County Building have been poured
Planters have been excavated from Bearden to Pearl Place
Back of the sidewalk planter has been excavated from Knox County Building to Baxter Ave.
Total Property Management is placing soil in excavated planters 
Progression has been pulling wire at 5th, Broadway, and Bernard

TWO-WEEK LOOK AHEAD
Signal system infrastructure work at Alexander Avenue
Sidewalks and bench landings installed from Knox County Building to Baxter Ave.
Resume storm work in Baxter after KUB gas line relocation is complete





September 20, 2018

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE Sept. 9, 2018
Curbs, sidewalks, driveway, and bus shelter pad in front of All Occasions have been poured
Curb cut at Pearl Place has been poured
Existing storm at East Scott Avenue has been tied to new storm system
Existing storm at All Occasions has been tied in to new storm system
Asphalt patching from East Anderson to Oklahoma where new storm was installed 
Signal control cabinets have been installed at 5th, Broadway, and Bernard

TWO-WEEK LOOK AHEAD
Signal system infrastructure work at Alexander Avenue
Begin work on curbs and sidewalks from Pearl Place to Baxter
Begin excavation for large planting beds from Pearl Place to Baxter Avenue
Resume storm work in Baxter after KUB gas line relocation is complete





September 06, 2018

TRAFFIC CONTROL AND SAFETY

No closures at this time.
 
PROGRESS SINCE AUGUST 23, 2018
All curbs, sidewalks, and patching in Bernard Avenue intersection is complete
Planter curbs from Bernard to Dameron have been poured
Driveway for Broadway Restaurant Equipment has been poured
Bus shelter pads at Bernard and Dameron have been poured
Curbs on east side of Central from Bearden Place to the north entrance to All Occasion Catering have been poured
Signal and interconnect infrastructure at Baxter Avenue is complete

TWO-WEEK LOOK AHEAD

Signal system infrastructure work at Alexander Avenue
Curbs, gutter pans, and sidewalks from Pearl Place to Baxter Avenue
Resume storm work in Baxter after KUB gas line relocation is complete





August 23, 2018

TRAFFIC CONTROL AND SAFETY

No closures at this time.

PROGRESS SINCE AUGUST 9, 2018

All curbs, sidewalks, and patching in Broadway intersection is complete
Regions Bank driveway is complete
Central Filling Station driveway is complete
Signal and interconnect infrastructures at Baxter Avenue is ongoing

TWO-WEEK LOOK AHEAD
Complete sidewalks and curbs in Bernard Avenue intersection
Complete signal system infrastructure work at Baxter Avenue
Curbs, gutter pans, sidewalks, and bus shelter pad from Bernard working toward Dameron





August 09, 2018

TRAFFIC CONTROL AND SAFETY

No closures at this time.
 
PROGRESS SINCE JULY 26, 2018
All storm drainage in somplete except for Baxter Avenue
Signal and interconnect infrastructure in Bernard Avenue is complete
Signal poles installed at 5th, Broadway, and Bernard
Sidewalks, curbs, and bump outs are complete in Bearden Place intersection
Sidewalks at Regions Bank are complete
Mock up panels have been poured and reviewed
a. Light sandblast finish chosen pending on site confirmation
b. Newport sand mix chosen over Nolichucky sand mix
Mulch installed from 5th Avenue to Bernard Avenue 

TWO-WEEK LOOK AHEAD
Complete sidewalk work at the Broadway intersection
Complete driveway at Regions Bank
Completed sidewalks and curbs in Bernard Avenue intersection
Begin signal system infrastructure work at Baxter Avenue





July 26, 2018

TRAFFIC CONTROL AND SAFETY

Closure of East Scott Wednesday, Thursday, and Friday for storm installation
 
PROGRESS SINCE JULY 12, 2018
Storm drainage in West Anderson Avenue is complete
Storm drainage at Oklahoma Avenue is complete
Bump-out curbs and sidewalks at 5th are complete
Signal and interconnect infrastructure in Broadway is complete
Sidewalks and bump outs are complete across the food truck park
Mock up panels have been poured and will be sandblasted tomorrow
a.  Aggregate size for specialy concrete mix
b.  Color difference between Newport sand and Nolichucky sand
 
TWO-WEEK LOOK AHEAD
Complete storm drainage in Scott Avenue
Complete sidewalk work at the Broadway intersection
Sidewalks, gutter pans, and bump outs in the Bearden Place intersection
Continue signal system infrastructure work at Bernard Avenue





July 12, 2018

TRAFFIC CONTROL AND SAFETY

Closure of the westbound right turn lane and shoulder of East Baxter Avenue until mid-July as storm drainage is installed 18-T-0410
Daily closures of West Anderson for storm installation, 18-T-0525

PROGRESS SINCE JUNE 28, 2018
Storm drainage in East Anderson is complete
Storm drainage in West Anderson will be completed this week
Bump-out curbs and sidewalks at 5th will be complete this week
Signal infrastructure in Broadway intersection will be complete this week
 
TWO-WEEK LOOK AHEAD
Resume storm drainage work on east side of Central from Alexander to Oklahoma
Begin storm drainage work in Oklahoma
Sidewalks, gutter pans, and bump outs from Magpie’s to Bearden Place on the east side of Central
Begin signal system infrastructure work at Bernard Avenue
Pour mock up panel for enhanced and blasted concrete finishes





June 28, 2018

TRAFFIC CONTROL AND SAFETY

Closure of the westbound right turn lane and shoulder of East Baxter Avenue until mid-July as storm drainage is installed 18-T-0410
Daily closures of east Anderson have been requested for next week for storm installation and asphalt patching.

PROGRESS SINCE JUNE 14, 2018
Added storm drainage (C-28 to C-28A) installed at Pearl Place
Storm in Baxter installed to C-45, storm work in Baxter currently stopped due to utility conflicts
Sidewalks, gutter pans, and bump-outs along the east side of Central are complete to Bernard Avenue
Sidewalks, gutter pans, and bump-outs along the east side of Central are complete from Fulton Place to north end of Magpies building

TWO-WEEK LOOK AHEAD
Install storm drainage in Anderson intersection
Resume storm drainage work in East Baxter Avenue once utility conflicts are resolved
Sidewalks, gutter pans, and bump outs from Fulton Place to Bearden Place on the east side of Central
Complete bump-out curbs and sidewalks at 5th Avenue
Continue signal system work at Broadway
Pour mock up panel for enhanced and blasted concrete finishes





June 14, 2018

TRAFFIC CONTROL AND SAFETY

Closure of the westbound right turn lane and shoulder of East Baxter Avenue until mid-July as storm drainage is installed 18-T-0410
Closure of East Baxter Avenue this Monday thru Thursday as structure C-41 is set and tied in to existing storm drainage in Central and Baxter 18-0427

PROGRESS SINCE MAY 31, 2018

Storm drainage installed from East Baxter to Pearl Place
Sidewalks, gutter pans, and bump-outs along the west side of Central are complete from Jennings to mid-block between Pruett Place and Bernard Avenue
Signals system infrastructure work, except for the foundation for pole B, is complete at 5th Avenue intersection, remaining pole bases and signal cabinet pedestal will be poured today

TWO-WEEK LOOK AHEAD
Install storm drainage in East Baxter Avenue
Sidewalks, gutter pans, and bump-outs from Fulton Place to Bearden Place on the east side of Central
Bump-out curbs and sidewalks at 5th Avenue
Continue signal system work at 5th and Broadway intersections





May 31, 2018

TRAFFIC CONTROL AND SAFETY

Temporary bike detour signage is in place
 
PROGRESS SINCE MAY 17, 2018
Storm drainage in Bearden Place is complete
Storm drainage line “B” is complete (all storm from Depot to Dameron Avenue)
Sidewalks along the west side of Central are complete from Broadway to Jennings
Bump-outs along east side of Central are complete to Fulton Place
Planting soil has been placed from Broadway to Fulton Place
Asphalt patching is complete in Bearden Place, across Central/Dameron, and along new curbs to Fulton Place

TWO-WEEK LOOK AHEAD
Install storm drainage from Baxter to Pearl Place
Continue sidewalks, gutter pans, and bump outs from Broadway to Bernard Avenue
Complete work on curbs and sidewalks surrounding Broadway intersection
Continue signal system work at 5th intersection and at Broadway





May 17, 2018

TRAFFIC CONTROL AND SAFETY

Traffic control permit in place for closure of Bearden Place this week between Central and Stewart Street.  This work is delayed until KUB can relocate a water main in conflict with the 18' RCP line connecting structures at Stewart Street.
Closure of North Central and Dameron Place next week to install storm drainage across North Central and Dameron Place

PROGRESS SINCE MAY 3, 2018
Storm drainage in Bearden Place is complete except for the 18” line connecting B-55 and B-56
Sidewalks along the east side of Central are complete to Broadway
Bump-out and added sidewalks at the SE corner of Broadway are complete
Roadway curb on NE corner of Broadway intersection is poured from Broadway to Regions Bank lower entrance
Signal foundations for poles A and D (5th Avenue) are complete
Planting soil has been placed from 4th to Broadway

TWO-WEEK LOOK AHEAD
Cross North Central and Dameron Place with new 18” storm and complete storm drainage line “B” (storm will be slightly more than 50% complete at this point)
Complete work on curbs and sidewalks surrounding Broadway intersection
Continue signal system work at 5th intersection and at Broadway





May 03, 2018

TRAFFIC CONTROL AND SAFETY

Closure of Bearden Place this week between Central and Stewart Street while storm drainage is installed 18-0273, permit request for next week has been submitted and approved
Lane shift today and tomorrow on Broadway at North Central while new curbs and sidewalks are poured on northeast corner of the intersection 18-T-0317
 
PROGRESS SINCE APRIL 19, 2018
All 36” storm drainage is now installed, ending at STR. B-51
Asphalt has been patched from Broadway to Fulton Place
Sidewalks along the east side of Central from 3rd to bump out at Broadway have been poured
Signal foundation work at 5th Avenue has begun

TWO-WEEK LOOK AHEAD
Complete storm drainage in Bearden Place intersection
Continue work on curbs and sidewalks surrounding Broadway intersection
Continue signal system work at 5th intersection and at Broadway
Installation of planting soil to begin on 5/9/18





April 19, 2018

TRAFFIC CONTROL AND SAFETY

Closure of Bearden Place between Central and Stewart Street requested for next week
COK has installed delineators in 5th to alert traffic to new design

PROGRESS SINCE APRIL 5, 2018
All storm drainage in the Broadway intersection is complete
Asphalt has been patched from Broadway to Fulton Place
Sidewalks along the west side of Central from 3rd to Broadway have been poured poured
Bump out and sidewalks along the east side of Central poured from 3rd approaching the antique store
Installation of the 36” storm has resumed and will be installed to structure B50.1 this week
Signal foundation at Broadway has been poured

TWO-WEEK LOOK AHEAD
Complete curbs and sidewalks from 3rd to Broadway
Install storm drainage in Bearden Place Intersection
Resume signal system work at 5th intersection and at Broadway
Begin installation of planting soil in planters that have been perc tested





April 05, 2018

TRAFFIC CONTROL AND SAFETY

Closure of Broadway intersection to install storm (TTCP 18-T-0191)
Broadway anticipated to be open by the end of the work day on Friday 4/6/18
Central will remain closed north and south of the Broadway intersection through next week
The outside right westbound lane of Broadway at Central will be closed through next week

PROGRESS SINCE MARCH 22, 2018
18” storm installed from South of Broadway to across 3rd Avenue, from structure from 3rd Avenue to Central and Broadway
Curbs, gutter drains, and sidewalks from Regions Bank’s north entrance to Fulton Place have been poured
Floor for storm structure at the center of the Broadway intersection has been poured
Storm crossing Broadway, from the center of the intersection to the southwest corner has been installed using 16” ductile pipe
Storm crossing Central southbound lanes, from from the center of the intersection to the southeast corner has been installed
Storm crossing Central northbound lanes, from from the center of the intersection to the northeast corner has been is delayed by KUB conflicts
16” ductile pipe used due to utility confines and elevation of existing 36” storm line
Water line conflict was resolved by KUB crews on 4/4/18
Gas line conflict will be addressed by KUB crews on 4/5/18 and 4/6/18

TWO-WEEK LOOK AHEAD
Complete storm drainage work in Broadway intersection
Construct curbs and sidewalks from 3rd to Broadway
Begin signal system work at 5th intersection and at Broadway





March 22, 2018

TRAFFIC CONTROL AND SAFETY

Closure of 3rd Avenue Thursday (March 22) and Friday (March 23) of this week to install storm pipe
Closure of 3rd Avenue Monday (March 26) and Tuesday (March 27) to install storm pipe
Closure of intersection of N Central and Broadway has been requested starting April 4 while the storm drainage is installed

PROGRESS SINCE MARCH 8, 2018
36" storm installed from existing structure at Fulton Place just North of Magpies
18" storm installed from just south of Broadway (at the antique store) to near 3rd Avenue
3rd Avenue will be swept just south of Broadway to near 3rd Avenue
Work on west side curbs and sidewalks from 4th Avenue to Magnolia is complete
Bus shelter pad at Crafty Bastard has been poured
Work north of Broadway on curbs, sidewalks, and entrance to Regions Bank has begun

TWO-WEEK LOOK AHEAD
Complete all storm drainage work between 3rd Avenue and Broadway
Storm drainage work in the Broadway intersection starting  Wednesday, April 4, 2018
Temporary lane closures for potholing of utilities will occur from now to Wednesday, April 4
Full closure of intersection beginning Wednesday, April 4
Work will begin at the tie-in in the Broadway intersection and fan out from there, starting with the Broadway crossing first





March 08, 2018

TRAFFIC CONTROL AND SAFETY

Parking spaces along Central from 5th and 4th are ready to be opened as soon as work (by others) on 5th is complete.
There will be daily closure of Fulton Place through Monday, March 12 to install 36" storm pipe

PROGRESS SINCE FEBRUARY 22, 2018
Storm drainage installation across 5th Avenue is complete and asphalt in 5th is patched
36" storm installed from existing structure at Regions Bank to the structure at Central Filling Station, and cross Fulton Place - progressed has been slowed by rock excavation
East side curbs, gutter pans, sidewalks and asphalt patching is complete to bump-out at 622 North Central (FM George)
Work on west side curbs and sidewalks from 4th Avenue to Magnolia has begun
Bus shelter pad at Crafty Bastard will be poured today

TWO-WEEK LOOK AHEAD
Continue installation of 36" storm line at the structure just north of Magpies
Complete curbs and sidewalks from 4th Avenue to Magnolia





February 22, 2018

TRAFFIC CONTROL AND SAFETY

Parking spaces along Central from 5th and 4th will remain barreled off until work is completed in this area
Asphalt patching will be complete by March 2nd and spaces will be re-opened
There will be a closure of Fulton Place on Friday, February 23 to install storm structure at this intersection
There will be daily lane closures on 5th Avenue on Monday, February 26 until 6pm Wednesday, February 28 to install storm drainage across 5th Avenue between N. Central Street and Williams Street
There will be daily closures of Fulton Place on Wednesday, February 28 through Friday, March 2 to install storm drainage across Fulton Place

PROGRESS SINCE FEBRUARY 8, 2018
KUB has corrected the utility conflicts at 5th Avenue and at the entrance to Regions Bank
36" storm installed from existing structure at Regions Bank to the structure at Central Filling Station, and should be to Fulton Place by the end of this week
Curbs and sidewalks at the corner of 4th Avenue and N. Central are complete
Bus shelter pad at the corner of 4th Avenue is complete

TWO-WEEK LOOK AHEAD
Continue installation of 36" storm line at the structure across Fulton Place
Complete storm drainage installation across 5th Avenue
Work on curbs and sidewalks from 4th Avenue to Magnolia
Patch asphalt from 5th Avenue to 4th Avenue





February 08, 2018

TRAFFIC CONTROL AND SAFETY

Parking spaces along Central from 5th and 4th will remain barreled off until work is completed in this area

PROGRESS SINCE JANUARY 25, 2018
Storm pipe installed from 4th Avenue to 5th Avenue
All ADA ramps at the Magnolia intersection have been replaced
Asphalt has been patched from Depot to Magnolia
Work has begun for curbs and sidewalks at the corner of 4th Avenue and N. Central

TWO-WEEK LOOK AHEAD
Begin installation of 36" storm line starting at Regions Bank
Crossing of Regions Bank entrance will be scheduled for a weekend or at night





January 25, 2018

TRAFFIC CONTROL AND SAFETY

Parking spaces along Central from 5th and 4th will remain barreled off until work is completed in this area

TWO-WEEK LOOK AHEAD
Storm drainage next to Old Knoxville High School Senior Living facility and working from 4th Avenue to 5th Avenue
Sidewalk and curb replacement from Depot to Magnolia will be poured Week of January 22 (weather permitting)
Tactile warning replacement at Magnolia
Begin installation of 36" storm line at Regions Bank
Asphalt patching from Depot to East 4th Avenue (weather permitting)





January 11, 2018

OPEN HOUSE

Open house for North Central Street project stakeholders
WHEN: 5 - 6:30 p.m. Thursday, Jan. 11, 2018
WHERE: City of Knoxville Public Works Service Center, 3131 Morris Ave.
WHO: Representatives from the City of Knoxville, Amec Foster Wheeler construction engineering inspections services, Vaughn and Melton Civil Engineering firm, Southern Constructors Inc. general contractor, Hedstrom Design landscape architecture, and Central Street residents, merchants and property owners

TRAFFIC CONTROL AND SAFETY

Closure of North Central between Depot and Magnolia on Wednesday, Thursday, and Friday (week of 1/8/2018) to install storm drainage
Parking spaces along Central from 5th and 4th will be barreled off starting week of January 15, 2018

CURRENT PROGRESS
Project laydown yard located at 1008 Tyson Street
Inlet protection installed from West Depot Avenue to Dameron Avenue
Construction signs installed
 ​
TWO-WEEK LOOK AHEAD
Storm drainage next to Old Knoxville High School Senior Living facility and working towards 4th Avenue.
Sidewalk and curb replacement from Depot to Magnolia
Tactile warning replacement at Magnolia