Work continues to progress on the reconstruction of the Henley Bridge in Knoxville.
Since the bridge was closed to traffic in January 2011, work has continued around the clock to demolish the existing structure.
Beginning Monday, March 28th, motorists can expect lane closures on Neyland Drive under the Henley Bridge as demolition activities continue.
The closures are as follows:
Monday March 28 through Thursday March 31, 9:00 a.m. - 4:00 p.m. - There will be temporary lane closures on Neyland Drive under the Henley Bridge to construct a median crossover in preparation for a traffic shift.
Monday April 4 through May 30, around the clock - Neyland Drive approaching the overhead Henley Bridge will be reduced to one lane in each direction. The eastbound traffic will be shifted to the westbound side of Neyland Drive in order to perform overhead bridge demolition over the eastbound lanes.
If you have questions concerning the bridge, feel free to stop by the Henley Community Center or call 865-577-6988.To find out more about the project, detours, Henley Bridge history and to view the project cameras you can visit
www.tn.gov/henley. You can also follow the project updates on twitter at
twitter.com/HenleyBridge.
- Henley Bridge Project Community Center