CONSTRUCTION PROJECTS STATUS - Updated October 15, 2018

Approach Trail for Pedestrian Bridge over Western Avenue Project
This project is for the construction of a portion of a multi-use trail from SR-62 (Western Avenue) up to the northern approach of a pedestrian / bicycle bridge being constructed under a TDOT funded roadway project.
• View Current Engineering Department Construction Status of Approach Trail for Pedestrian Bridge over Western Avenue Project [PDF]
• View additional information provided by the Tennessee Department of Transportation regarding State Route 62 (Western Avenue) Schaad Road to Copper Kettle Road

Cedar Lane Sidewalk Project

The Cedar Lane Sidewalk Project consists of the construction of approximately 2,000 linear feet of new sidewalk on the south side of Cedar Lane between Pratt Road and Haynes-Sterchi Road. The proposed sidewalk will extend the existing sidewalk on Cedar Lane to the Windsor Court Apartments. This project also includes a pedestrian crossing across the Norfolk Southern Railroad.
• View Current Engineering Department Construction Status of Cedar Lane Sidewalk Project [PDF]

Colonial Circle Sidewalk Replacement at N Broadway Project
The Colonial Circle Sidewalk Replacement at N Broadway Project consists of the installation of structural concrete to replace the sidewalk over and next to the box culvert at Colonial Circle and N. Broadway and any other work needed to complete the project.
• View Current Engineering Department Construction Status of Colonial Circle Sidewalk Replacement at N Broadway Project [PDF]

Cumberland Avenue Streetscapes Phase I & II Project
Cumberland Avenue between Seventeenth Street and Twenty Second Street has been transformed into a safer, more pedestrian-friendly corridor with new utility infrastructure, wider sidewalks, improved traffic flow, a raised median and left-turn lanes at intersections. The public investment of $25 million has helped leverage more than $190 million in private investment.
• View Current Engineering Department Construction Status of Cumberland Avenue Streetscapes [PDF]
• View additional information provided by the Redevelopment Office regarding the Cumberland Avenue Streetscapes Project

2018 Facilities Paving Project
This project consists of paving the Parking lot at West Hills / John Bynon Park near Sheffield Drive and near N Winston Road, the parking lot at Milton Roberts Recreation Center, the parking lot at the Solid Waste Facility at Elm Street and the Northwest Middle School Greenway.
• View Current Engineering Department Construction Status of 2018 Facilities Paving Project [PDF]
• Hot Temps Bring Hot, New Paving Projects

Fire Headquarters Roof Project
This project will replace the roof at the Fire Department Headquarters that has exceeded its service life and has begun leaking.
• View Current Engineering Department Construction Status of Fire Headquarters Roof Project [PDF]

Fort Dickerson Parking Lot Improvements
This project will provide improvements to the Augusta Avenue entrance to the Fort Dickerson Quarry and the parking that is located near the swimming area inside the park. The project includes a new attractive gateway entrance, improves the existing gravel lot with curbs and paving, hardscapes, and landscaping at the entrance and parking lot. Additionally, infrastructure for future phases of improvements to the quarry that would require utilities will be installed.
• View Current Engineering Department Construction Status of Fort Dickerson Parking Lot Improvements Project [PDF]
• View additional information provided by the Parks and Recreation Department regarding Fort Dickerson Park

Gay Street Crosswalks Project
This project will replace eight crosswalks with stamped stained concrete on Gay Street from Summit Hill Drive to Union Avenue.
• View Current Engineering Department Construction Status of Gay Street Crosswalks Project [PDF]
• View Gay Street Crosswalks Closures Map [PDF]

Gleason Drive Sidewalk Project
This project will construct approximately 1,800 linear feet of new sidewalk along Gleason Drive between Downtown West Boulevard and Bearden High School.
• View Current Engineering Department Construction Status of Gleason Drive Sidewalk Project [PDF]

Grainger Avenue Bridge Replacement Project

The Grainger Avenue Bridge Project consists of the replacement of the bridge on Grainger Avenue over First Creek and a new sidewalk connection along Grainger Avenue to N Sixth Avenue. This replacement bridge will increase the opening over First Creek to help alleviate flooding issues in the vicinity of this project. Additionally, new gas and water lines will be installed as part of this project.
• View Current Engineering Department Construction Status of Grainger Avenue Bridge Replacement Project [PDF]

KAT Summit Hill Transit Stop Project
This project includes the construction of a new sidewalk that will provide an accessible connection between Summit Towers and the existing KAT stop on Summit Hill Drive near Walnut Street. Additionally, the existing stop will be improved to include a new bus shelter and pedestrian scale lighting will be installed along the new sidewalk.
• View Current Engineering Department Construction Status of KAT Summit Hill Transit Stop Project [PDF]
• View additional information regarding Knoxville Area Transit

Magnolia Avenue Gateway Monument Project
Coincident with the Magnolia Avenue Streetscapes Project, a gateway monument sign will be installed at the northeast corner of E Magnolia Avenue and Jessamine Street.
• View Current Engineering Department Construction Status of Magnolia Avenue Gateway Monument Project [PDF]
• View additional information provided by the Redevelopment Office regarding the Magnolia Avenue Streetscape Project
• View the Magnolia Avenue Streetscapes website
• Magnolia Avenue Streetscapes Project Blog

Magnolia Avenue Streetscapes Phase I Project
This project will replace the existing sidewalks and curb, and reconstruct the roadway as needed along E Magnolia Avenue between Jessamine Street and N Myrtle Street to provide for better pedestrian access while allowing for street amenities such as trees, lighting, etc.
• View Current Engineering Department Construction Status of Magnolia Avenue Streetscapes Phase I Project [PDF]
• View additional information provided by the Redevelopment Office regarding the Magnolia Avenue Streetscapes Project
• View the Magnolia Avenue Streetscapes website
• Magnolia Avenue Streetscapes Project Blog

600 Block of Market Street Project
This project will reconstruct Market Street and adjoining sidewalks between Clinch Avenue and W Church Avenue.
• View Current Engineering Department Construction Status of 600 Block of Market Street Project [PDF]

Merchant Drive at Clinton Highway Intersection Improvements Project
The Merchant Drive/Clinton Highway project consists of constructing intersection improvements to allow for more efficient turning movements and storage for vehicles, extending sidewalks to provide access to nearby KAT bus stops and adding safer pedestrian crossings with signals and refuge islands. Additionally, gas, water, and sewer lines will be relocated for KUB as part of this project.
• View Current Engineering Department Construction Status of Merchant Drive at Clinton Highway Intersection Improvements Project [PDF]

N Central Streetscapes Project
The N Central Streetscapes Project includes formalizing the temporary complete-streets conversion along with other streetscapes improvements on the N Central Street corridor from Woodland Avenue to Depot Avenue. The project will incorporate bike lanes, on-street parking and wider sidewalks. KUB has completed water and gas relocations in advance of this streetscape improvements project.
• View Current Engineering Department Construction Status of N Central Streetscapes Project [PDF]
• View additional information provided by the Redevelopment Office regarding the N Central Streetscapes Project
• North Central Street Project Blog

2017 Neighborhood Drainage Project

This project will address drainage issues at various sites throughout the City and include: W Glenwood Avenue, Maplehurst Court, Noelton Drive and Upland Avenue.
• View Current Engineering Department Construction Status of 2017 Neighborhood Drainage Project [PDF]

2017 Resurfacing Project
This project is the City’s annual resurfacing program and includes approximately 45.5 equivalent miles of resurfacing citywide. Additionally, in compliance with the Supplemental Memorandum of Understanding and Agreement between the City of Knoxville and Knoxville Utilities Board, and at KUB’s request, 5.9 additional equivalent miles have been included for resurfacing streets that were damaged through its utility cuts.
• View Current Engineering Department Construction Status of 2017 Resurfacing Project [PDF]
• View additional information regarding the annual Citywide Resurfacing Program

2018 Resurfacing Project
This project is the City’s annual resurfacing program and includes approximately 49.5 equivalent miles of resurfacing citywide. Additionally, in compliance with the Supplemental Memorandum of Understanding and Agreement between the City of Knoxville and Knoxville Utilities Board, and at KUB’s request, 4.1 additional equivalent miles have been included for resurfacing streets that were damaged through its utility cuts.
• View Current Engineering Department Construction Status of 2018 Resurfacing Project [PDF]
• View additional information regarding the annual Citywide Resurfacing Program
• Hot Temps Bring Hot, New Paving Projects

2018 Sidewalk Replacement Project
This project will remove and replace sidewalk at over fifteen locations throughout the city.
• View Current Engineering Department Construction Status of 2018 Sidewalk Replacement Project [PDF]

S Castle Street Sidewalk Project
The City of Knoxville received a Congestion Mitigation and Air Quality Grant (CMAQ) grant for pedestrian improvements in the Park City neighborhood. This project will construct a missing sidewalk link along S Castle Street from Martin Luther King Jr Avenue to Claude Walker Park at Wilson Avenue.
• View Current Engineering Department Construction Status of S Castle Street Sidewalk Project [PDF]

Suttree Landing Park Roadway Improvements, Phase 1A Project
This project consists of approximately 2,988 LF (0.56 miles) of new roadway construction north of Langford Avenue between Barber Street and Foggy Bottom Street with new asphalt pavement, concrete sidewalk, concrete curb, landscaping, rip-rap, tree plantings and irrigation, decorative street lighting, site furnishings, pavement markings, waterline, sewer and underground electrical utility construction and any necessary drainage work and other work necessary to complete the project.
• View Current Engineering Department Construction Status of Suttree Landing Park Roadway Improvements, Phase 1A Project [PDF]
• City Blog: Bird's Eye View: Suttree Landing Park
• South Waterfront Blog


DESIGN PROJECTS STATUS - Updated October 5, 2018

Amherst Road Slope Stabilization Project
Designer: CDM Smith
Projected Bid Date: Fall 2019
This design project is located along the south side of Amherst Road between 1950 Amherst Road and 2004 Amherst Road. Results of subsurface exploration in this section of roadway shoulder and slope leading down to an existing CSX railroad track indicate that the slope is stable. However, the use of gabion baskets to re-establish the roadway shoulder and protect the roadway from additional shoulder failures is proposed. Since the project area is located within railroad right-of-way, significant coordination with CSX is required.

Atlantic Avenue Sidewalk Project

Designer: Cannon & Cannon, Inc.
Projected Bid Date: Summer 2020
This project is will construct approximately 3,000 linear feet of sidewalk between N Broadway and Pershing Street.

Boyd Bridge Pike Sidewalk Project
Designer: City of Knoxville
Projected Bid Date: Summer 2019
This project will construct a sidewalk between Rosalyn Drive and Brooks Avenue.

Broadway Streetscapes Project
Designer: Barge Design Solutions, Inc.
Projected Bid Date: Summer 2020
This project consists of a new shared use path extending First Creek Greenway from near Cecil Avenue to near Woodland Avenue.

Buffat Mill Road Sidewalk Project
Designer: City of Knoxville
Projected Bid Date: Summer 2019
This project will construct approximately 2,550 linear feet of new sidewalk along Buffat Mill Road between Whittle Springs Road and Bridalwood Drive.
• View additional information provided by the Mayor’s Office regarding New Sidewalk Projects Across the City.

Cal Johnson Recreation Center Renovation Project
Designer: Community Tectonics Architects, Inc.
Projected Bid Date: Winter 2019
This project will provide renovations to the recreation center.
• Residents Attend Public Meeting for Cal Johnson Recreation Center Renovations
• View additional information provided by the Parks and Recreation Department regarding Cal Johnson Recreation Center

Coker Avenue Sidewalk Project
Designer: City of Knoxville
Projected Bid Date: Spring 2020
The project will construct new sidewalk between Nadine Street and Whittle Springs Road.

Cumberland Avenue Signals Project
Designer: City of Knoxville
Projected Bid Date: Spring 2019
This project will replace signals, curb cuts and crosswalks on Cumberland Avenue at Eleventh Street, Thirteenth Street, Circle Drive, James Agee Street and Volunteer Boulevard.

Cumberland Estates Recreation Center Roof Project
Designer: City of Knoxville
Projected Bid Date: Spring 2019
This project will replace the roof at the Cumberland Estates Recreation Center that has exceeded its service life.
2019 Curb Cuts Project
Designer: City of Knoxville
Projected Bid Date: September 2018
This project will install or improve curb cuts in existing sidewalks to make them fully accessible. It is generally the intent of this project to install curb cuts at locations that are planned to be resurfaced within the next few years.

Fire Headquarters Driveway Project
Designer: Foundation Systems Engineering, P.C.
Projected Bid Date: Winter 2019
This project will replace the existing asphalt driveway with a concrete driveway at the Fire Department Headquarters.

Fire Station #4 (Park City / Parkridge) Renovations Project
Designer: Michael Brady, Inc.
Project Bid Date: Fall 2018
This project will renovate living quarters, replace wiring and plumbing. 

I-275 Business Park Access Improvements Project
Designer: CDM Smith
Projected Bid Date: Fall 2018
The City of Knoxville is proposing to extend Blackstock Avenue approximately 1100 feet from Fifth Avenue to Bernard Avenue. Additionally, the project will extend approximately 1,600 feet north along Marion Street to Baxter Avenue and approximately 325 feet east and 325 feet west along Baxter Avenue. The proposed improvements will include a new two-lane road consisting of 11-foot travel lanes, curb and gutter, a 5-foot sidewalk and a ten-foot multipurpose trail from Fifth Avenue to Bernard Avenue. Improvements will also be made to Marion Street from Bernard Avenue to Baxter Avenue, including the addition of curb and gutter, sidewalk and greenway and the realignment of Marion Street from Dameron Avenue to Baxter Avenue. Minor intersection improvements are proposed for Fifth Avenue and Blackstock Avenue, Blackstock Avenue at Bernard Avenue and Marion Street and Marion Street at Baxter Avenue.
• View additional information provided by the Redevelopment Office regarding the I-275 Business Park Access Improvements Project [PDF]

Jackson Avenue Ramps Project
Designer: Vaughn & Melton Consulting Engineers, Inc.
Projected Bid Date: Winter 2019
The Jackson Avenue Ramps are included within the TDOT Bridge Inventory and are inspected on a bi-annual basis. The poor rating of the ramps resulted in qualification for participation in the federal bridge replacement program. This project will replace both the east and west ramps of Jackson Avenue at Gay Street.
• View Current Engineering Department Design Status of Jackson Avenue Ramps Project [PDF]
• View additional information provided by the Redevelopment Office regarding Jackson Avenue Projects

Kingston Pike Complete Connections Project
Designer: CDM Smith
Projected Bid Date: Winter 2019
This project uses funding the City received from TDOT through the Multimodal Access Grant Program for the design of improvements on Kingston Pike that address the gaps in the sidewalk network, provide wider shoulders in the pinch points in the bicycle network between Wesley Road and Golfclub Road and provide better connections to KAT bus stops. The design will also include pedestrian crosswalks and pedestrian signals across Kingston Pike and Papermill Drive and a covered bus shelter near Golfclub Road.
• View additional information regarding the TDOT grant for the Kingston Pike Complete Connection Project

Lancaster Drive Sidewalk Project
Designer: City of Knoxville
Projected Bid Date: Fall 2019
This project will construct sidewalk between Tilson Street and Sevierville Pike.

Liberty Street Multimodal Project
Designer: Barge Design Solutions, Inc.
Projected Bid Date: Summer 2019
This project creates a bicycle and pedestrian connection between Middlebrook Pike and Sutherland Avenue. It adds bicycle facilities on Division Street and Liberty Street and installs a new sidewalk on Liberty Street, connecting to two adjacent sidewalks. Bus stop, crosswalk and pedestrian signals improvements will also be included as part of this project.

Loves Creek Greenway Project
Designer: Fulghum, MacIndoe, & Associates, Inc.
Projected Bid Date: Winter 2019
This project will make a greenway connection between Millertown Pike and Buffat Mill Road along Loves Creek. The proposed greenway will connect to existing sidewalk at the intersection of Millertown Pike and Loves Creek Road and utilize an existing concrete greenway on the Walmart property at 3051 Kinzel Way.
• View additional information provided by the Parks and Recreation Department regarding the existing Loves Creek Greenway

Magnolia Avenue Streetscapes Phase II Project
Designer: Barge Design Solutions, Inc.
Projected Bid Date: Fall 2018
This project will replace the existing sidewalks and curb, and reconstruct the roadway as needed along E Magnolia Avenue between N Myrtle Street and N Bertrand Street to provide for better pedestrian access while allowing for street amenities such as trees, lighting, etc.
• View additional information provided by the Redevelopment Office regarding the Magnolia Avenue Streetscape Project
• View the Magnolia Avenue Streetscapes website
• Magnolia Avenue Streetscapes Project Blog

Middlebrook Pike at Lake Brook Boulevard Sidewalk Project
Designer: QK4
Projected Bid Date: October 2018
This project will consist of constructing approximately 200 linear feet of new sidewalk along the south side of Middlebrook Pike and will include bus stop and pedestrian signal improvements at the intersection.

Milton Roberts Recreation Center Roof Project
Designer: City of Knoxville
Projected Bid Date: Spring 2019
This project will replace the roof at the Milton Roberts Recreation Center that has exceeded its service life.
Mineral Springs Bridge Replacement Project
Designer: Alfred Benesch & Company
Projected Bid Date: October 2018
This design project will provide the surveying and design services for a bridge replacement project that will include the design of a new bridge, drainage, and a new sidewalk connection to Walker Boulevard. This new bridge will be sized based on recommendations in the First Creek Watershed Stormwater Management Master Plan.

Northwest Greenway Connector Project
Designer: Barge Design Solutions, Inc.
Projected Bid Date: Spring 2019
This project will construct a greenway connection between Victor Ashe Park and the proposed pedestrian bridge over Western Avenue (SR-62) which is being constructed by the Tennessee Department of Transportation at the intersection of Ball Camp Pike and Western Avenue.
• View additional information provided by the Parks and Recreation Department regarding the existing Northwest Greenway

Old Broadway Sidewalks Project
Designer: Barge Design Solutions, Inc.
Projected Bid Date: Spring 2019
This project will construct new sidewalk along Old Broadway from N Broadway to Mineral Springs Avenue and will also include pedestrian signs at N Broadway and Mineral Springs Avenue.

Palmetto Road Sidewalk Project
Designer: City of Knoxville
Projected Bid Date: Winter 2019
This project will construct approximately 1,150 linear feet of new sidewalk along Palmetto Road between Western Avenue and Landon Drive.
• View additional information provided by the Mayor’s Office regarding New Sidewalk Projects Across the City.

Palmetto Road Sidewalk Phase II Project
Designer: City of Knoxville
Projected Bid Date: Fall 2019
This project will construct new sidewalk between Landon Drive and Sullivan Road.

Pleasant Ridge Road Phase II Project

Designer: Gresham, Smith and Partners
Projected Bid Date: Summer 2019
This design project includes a safety audit of Pleasant Ridge Road between Merchant Drive and the City limits and includes updated studies of crash history and traffic volumes and preparation of a report to TDOT that makes recommendations on improvements that are needed based on this data. This report will follow TDOT's Expedited Delivery Project format which would allow the City to modify the scope of the original design project without jeopardizing any federal funding associated with this project. Once this report is accepted by TDOT, the City will be advertising for design services to modify the original construction plans based on the recommendations in this report. Improvements include the addition of turn lanes at Walnoaks Road, Sullivan Road and Moss Creek Road.

Prosser Road Impound Building Project
Designer: Thomas Caldwell, Architect
Projected Bid Date: Fall 2018
This project will construct a new building for the vehicle impound lot.

Resubdivision of Sanitary Laundry Property at 625 N Broadway Project
Surveyor: City of Knoxville

2019 Resurfacing Project
Designer: City of Knoxville
Projected Bid Date: November 2018
This project is the City’s annual resurfacing program.
• View additional information regarding the annual Citywide Resurfacing Program

Second Creek Greenway Project
Designer: CDM Smith
Projected Bid Date: Fall 2019
The Second Creek Greenway Project will make a greenway connection between Worlds Fair Park and Bernard Avenue, generally located along Second Creek.
• View additional information provided by the Parks and Recreation Department regarding the existing Second Creek Greenway

Sevier Avenue Improvements Project
Designer: Vaughn & Melton Consulting Engineers, Inc.
Projected Bid Date: Spring 2019
The Departments of Redevelopment and Engineering have worked in cooperation to implement the construction of new streetscape improvements to support South Waterfront Redevelopment efforts. As part of the South Waterfront Vision Plan, an improved roadway network will create accessibility to the City’s newest waterfront park, Suttree Landing Park. This project includes new streetscape improvements along Sevier Avenue which will extend from Davenport Road to a new roundabout at Sevier Avenue, Foggy Bottom Street and Island Home Avenue intersections.
• View additional information provided by the Redevelopment Office regarding the Sevier Avenue Improvements Project
• South Waterfront Blog

Sheffield Drive Sidewalk Project

Designer: City of Knoxville
Projected Bid Date: Summer 2019
This project will construct new sidewalk between the existing sidewalk near Portsmouth Road to Wesley Road.

2019 Sidewalk Replacement Project
Designer: City of Knoxville
Projected Bid Date: Fall 2018
This project will include sidewalk replacement along some sections of Washington Pike, Middlebrook Pike, Haynes Place, Hannah Avenue, Clearview Street, Clinch Avenue, Laurel Avenue, Eighteenth Street, S Seventeenth Street.  Other sites are being evaluated at this time.

Sullivan Road Sidewalk Project
Designer: City of Knoxville
Projected Bid Date: Summer 2019
The project will construct new sidewalk between Walnoaks Road and Palmetto Road.

Urban Wilderness Gateway Project
Designer: Vaughn & Melton Consulting Engineers, Inc.
Projected Bid Date: Spring 2019
This project will construct an entrance to the Urban Wilderness and park amenities in the area south of the James White Parkway terminus.

Washington Pike from I-640 to Murphy Road Project
Designer: CDM Smith
Projected Bid Date: 2019
Washington Pike, north from Interstate 640 to Murphy Road is proposed as four traffic lanes with median and turn lanes as required. The project length of is approximately 1.7 miles. The proposed typical section is expected to include four traffic lanes with median and turn lanes as required, 4' bike lanes, curb and gutter, 5' sidewalks with adjacent utility strip on both sides of the road, and some combination of storm water treatment (infiltration trenches, detention, basins, etc.) that will be designed to address the city's requirements for storm water management.
• View Current Engineering Department Design Status of Washington Pike from I-640 to Murphy Road Project [PDF]

Wilson Avenue Sidewalk Project
Designer: City of Knoxville
Projected Bid Date: Spring 2019
This project will construct approximately 1,400 linear feet of new sidewalk along Wilson Avenue between S Chestnut Street and S Harrison Street.
• View additional information provided by the Mayor’s Office regarding New Sidewalk Projects Across the City.

E Woodland Avenue Complete Streets Project
Designer: Kimerly-Horn and Associates, Inc.
Projected Bid Date: Spring 2020
In 2016, City Council approved a resolution to execute an agreement with Kimley-Horn and Associates, Inc. for design of four bicycle infrastructure projects. The design of the projects are occurring in two phases. The first phase, which was completed in 2017, developed a functional plan for each project. This consisted of traffic studies, road safety audits, surveying, stakeholder workshops, public meetings and facility alternative analysis, and resulted in recommendations of a facility type and construction cost estimates for each project location. Now that this phase of the project is complete, a second contract is needed for each project for the development of construction drawings. This project has two phases and contracts because the cost estimates for the development of construction drawings could not be determined until all the tasks included in the previous resolution has been completed.

COMPLETED PROJECTS - Click Project Name For More Information

Completed Projects 2011
Downtown Sidewalk Replacement [PDF]
First Creek Drainage Improvements [PDF]
Gay Street Streetscapes Project (300 & 600 Blocks) [PDF]
North Central Striping Project [PDF]
Papermill Bluff Greenway Project [PDF]

Completed Projects 2012
2012 ADA Curb Cut Program [PDF]
2012 Alley Paving Project [PDF]
Beaumont Elementary Sidewalk Improvements [PDF]
Central Avenue Pike at Merchant Drive Improvements [PDF]
2011 Citywide Crosswalk Safety Program [PDF]
Eutaw Place Roadway Stabilization Project [PDF]
Georgia Street Bridge Removal Project [PDF]
Middlebrook Pike Sidewalk Improvements Project [PDF]
2012 KAT Bus Stop Project [PDF]
Morningside Park Improvements Project [PDF]
2011 Sidewalk Replacement Project [PDF]
2011 Resurfacing Project [PDF]
Sutherland Avenue Bridge Repair Project [PDF]

Completed Projects 2013
2013 ADA Curb Cut Program [PDF]
Cherokee Trail Safety Improvements Project [PDF]
City View Riverwalk Project [PDF]
Gallaher View Sidewalk Project [PDF]
Middlebrook Pike at Twenty-First Street Intersection Improvements Project [PDF]
Millertown Pike Roadway Improvements Project [PDF]
2012 Neighborhood Drainage Project [PDF]
2012 Resurfacing Project [PDF]
Site Development Detention Pond Improvement Project [PDF]
Third Creek Greenway Bridge Replacement Project [PDF]
Williams Creek Drainage Improvements Project [PDF]

Completed Projects 2014
2013 Alley Paving Project [PDF]
Cherokee Trail Drainage Improvements Project [PDF]
2013 Citywide Crosswalk Safety Program [PDF]
E Woodland Avenue Sidewalk Project [PDF]
Fountain City Lake Repair Project [PDF]
400 & 500 Blocks N Gay Street Streetscapes Project [PDF]
Glenwood Avenue Bridge Replacement Project [PDF]
Greenway Drive Bridge Repair Project [PDF]
Inskip Ballfield - Second Creek Restoration Project [PDF]
Loves Creek Road Bridge Rehabilitation Project [PDF]
Prosser Road Drainage Improvements Project [PDF]
2013 Resurfacing Project [PDF]
2014 Resurfacing Project [PDF]
2014 Sidewalk Improvements Project [PDF]
2012 Sidewalk Replacement Project [PDF]

Completed Projects 2015
2014 Alley Paving Project [PDF]
2014 Curb Cuts Project [PDF]
2015 Curb Cuts Project [PDF]
Downtown Knoxville Wayfinding Project [PDF]
Fort Dickerson Road Realignment Project [PDF]
Knoxville Municipal Golf Cart Path Paving Project [PDF]
Lakeshore Park Large Buildings Abatement & Demolition Project [PDF]
Lakeshore Park Small Buildings Abatement & Demolition Project [PDF]
Sutherland Avenue Sidewalk Improvements Project [PDF]
Whittle Springs Golf Cart Path Paving Project [PDF]

Completed Projects 2016
2016 Alley Paving Project [PDF]
Bridge Rehabilitation Project (Ed Shouse Drive) [PDF]
Cross Park Drive Drainage Project [PDF]
Downtown Sidewalk Repairs Project [PDF]
Fort Sanders Sidewalk Project [PDF]
Improvements on W Jackson Avenue and on Henley Street Project [PDF]
Kirkwood KAT Superstop Project [PDF]
Knox Blount Greenway Phase I Project [PDF]
Lakeshore Central Service Building Roofing Project [PDF]
Lakeshore Park Site Demolition Project [PDF]
Old City Streetscapes [PDF]
2015 Resurfacing Project [PDF]
2015 Sidewalk Replacement Project [PDF]
Westland Drive Drainage and Bridge Improvements Project [PDF]
Will Skelton Greenway Stabilization Project [PDF]

Completed Projects 2017
Caswell Park Storage Building Project [PDF]
N Central Street Streetscapes - 200 Block Project [PDF]
2016 Curb Cuts Project [PDF]
Deane Hill Recreation Center Roof Project [PDF]
Facilities Paving at 913 E Fifth Avenue Project [PDF]
Fire Station #18 Reroofing Project [PDF]
Fire Station #18 Fascia Repair and Painting Project [PDF]
Fort Dickerson Gateway Park Project [PDF]
Fort Sanders Fire Station #9 Floor Modifications Project [PDF]
Gay Street Brick Sidewalk Repair Project [PDF]
700 Block S Gay Street Improvements Project [PDF]
Gleason Drive Sidewalk Project [PDF]
Holbrook Drive Bridge Replacement Project [PDF]
Hill Avenue Viaduct Expansion Joint Repair Project [PDF]
James White Parkway Guardrail Project [PDF]
KAT Employee Parking Lot Project [PDF]
Lakeshore Parking Lot Lights Project [PDF]
Marble Alley Streetscapes Project [PDF]
2014 Neighborhood Drainage Project - Phase I [PDF]
Ray Mears Boulevard Sidewalk Project [PDF]
2016 Resurfacing Project [PDF]
South Central Street Fence Project [PDF]
Sutherland Avenue Bridge Rehabilitation Project [PDF]
Suttree Landing Park Improvements, Phase 1B Project [PDF]
W Young High Pike Sidewalk Project [PDF]
Wesley Road Sinkhole Repair Project [PDF]
Wilkerson Road Bridge Replacement Project [PDF]

Completed Projects 2018
2017 Curb Cuts Project [PDF]
2018 Curb Cuts Project [PDF]
Fire Station #18 Fascia Repair and Painting Project [PDF]
First Creek Greenway Project [PDF]
2017 Neighborhood Drainage Phase II Project [PDF]
Old City Streetscapes - Jackson Avenue Phase I Project [PDF]
Pleasant Ridge Road at Wilson Road Sidewalk Project [PDF]
2017 Sidewalk Replacement Project Project [PDF]
South Knoxville Community Center Roof Project [PDF]
W Jackson Avenue Streetscapes [PDF]