A bridge replacement and road improvements to Westland Drive during the
next six months will require lane and road closures at various times
along the road between South Northshore Drive and Morrell Road.
The Westland Drive Drainage & Bridge Improvements Project is
scheduled to begin Monday, March 23. The duration of the project is 180
calendar days. The work consists of replacing the box culvert bridge on
Westland Drive just east of Craigland Court, channel improvements, and
utility relocations -- along with roadway improvements on Westland Drive
near Rotherwood Drive.
In an effort to minimize the flooding of Westland Drive near Craigland
Court, the existing drainage channel along Westland Drive will be
improved. The improvements include the widening of approximately 1,000
feet of the existing channel. To improve traffic safety, the new
drainage channel will be shifted farther north, away from the westbound
travel lane of Westland Drive, in order to provide a 10-foot shoulder
along Westland Drive from Craigland Court to Craig Road.
One-lane closures during the hours of 9 a.m.-3 p.m. are expected along
sections of Westland Drive between South Northshore Drive and Morrell
Road throughout the duration of the project.
In addition, Westland Drive will be completely closed to through traffic
between South Northshore Drive and Morrell Road for 60 days beginning
Monday, May 11, to allow for the replacement of the box culvert bridge.
The detour route for the road closure will be Northshore Drive to
Morrell Road to Westland Drive.
The exact point of closure will be the bridge nearest Craigland Court.
During the closure, motorists from Northshore Drive will be able to
access Kingsford Way and the eastern end of Sherwood Drive, and
Craigland Court residents will have access via Westland Drive to the
west.
To discourage cut-through traffic on neighborhood streets, temporary
speed humps will be installed on Craig Road, Sherwood Drive, and Stone
Mill Drive.