Beginning in November 2023 and lasting through June 2024, KUB and contractor crews will upgrade water and wastewater infrastructure along N. Broadway between Bluff Avenue and Oglewood Avenue. This includes replacement of approximately 3,000 linear feet of 90-year-old, 10-inch water main with new 8- and 10-inch ductile iron water main in two phases from November 2023 through March 2024, and approximately 2,000 linear feet of wastewater main in three phases starting in January through June 2024.
Water System Work (Nov. 2023 – March 2024)
Work will take place Monday through Friday, overnight between 7 p.m. - 6 a.m. with daytime work hours on Saturday and Sunday.
Inside north- and southbound lanes and the center turn lane will be closed on N. Broadway during work hours. Curbside north- and southbound lanes will remain open.
Wastewater System Work (January - June 2024)
Expect continuous 24-hour work days, with continuous closure of northbound and center turn lanes with traffic flow shifted to one northbound and one southbound lane using the southbound lanes.
Project timeline:
Phase 1 Water
Cecil Avenue to Lawson Avenue
Nov. 2023 - Feb. 2024
Phase 2 Water
Lawson Avenue to Oglewood Avenue
January - March 2024
Phase 1 Wastewater
West side of N. Broadway across from Lawson Avenue
January 2024
Phase 2 Wastewater
Near entrance to First Creek Greenway
Jan. - March 2024
Phase 3 Wastewater
Cecil Avenue to Coker Avenue
March - June 2024
More information and updates on this and other KUB projects is available at
https://www.kub.org/about/community/construction-map.